Will shoddy design prove a dampener for Chennai’s Metro pride?

With exposed metal bars, cracking panes and flawed design leading to overheating, Metro stations in the city leave a lot to be desired.

Let us make it quite clear at the outset – we are delighted that the city has a metro rail service in operation, albeit a mere fraction of what ought to have been running by now. Those who use the facility profess to be quite happy with it – it saves time, the stations are clean and Chennai Metro Rail Limited has also organised some kind of last-mile connectivity by pressing into service local auto-rickshaws and taxicabs. But what is of worry, apart from the high fares, is the shoddy workmanship of the stations and the numerous technical glitches that the actual operation itself suffers from.

True, the latter can be teething troubles, but not the former. There is really no excuse for poor quality construction.

A correspondent who specialises in civil projects has actually taken the pains to go around the stations and photographically document some of what has gone wrong. These range from major to minor lapses. Among the former you would include unfinished concrete cladding, thereby exposing mild-steel handrails.

Also in this category would be water-logging due to improper finishing of the surfaces of the stations. The ceilings are already disfigured even though the monsoon has not arrived. Exposed metal bars that form the actual skeleton of the station structures pose a bigger threat in the long term – these can corrode, thereby weakening the buildings themselves.

Of more immediate concern are the falling roof tiles and cracking window panes, both of which have become routine occurrences. These have injured a few commuters as well. No less an authority than IIT Madras has been moved to comment that all of these are indications of poor workmanship.

CMRL responded with patchwork – removing fifty tiles that were identified as likely to fall and covering all the exposed spaces with cement and paint. The idea of replacing with new tiles was given up. If that be the case, why was tiling done in the first place at an added expense? There are several minor issues as well – improperly finished junction boxes and switches, crooked signboards and gaping holes in station display panels. Not many are likely to notice these, but those who do are left unimpressed.

There have been operation glitches as well. The signalling systems failed three days running in one week of October, resulting in trains being delayed. Irate commuters had no choice but to take to bus transport, thereby negating the very purpose of the Metro. The level of air-conditioning has also come in for complaint. The stations are invariably hot, leaving commuters enervated. As for the staff, who have to spend the whole day underground, their plight can only be imagined.

CMRL has responded to this complaint by stating that the air-conditioning system is only partially operational. Many of its units are turned off to save power as the commuter traffic still remains low. The question then arises that if this be the quality of cooling with low patronage, how will it be when the Metro runs to full capacity?

A second reason for the warmth in the stations once again points to shoddy design – the hot air in the tunnels apparently seeps through gaps in the station doors, thereby heating up the public areas. In a hot city like Chennai, surely this ought to have been thought through even at the design stage? It is too late now to do anything about it.

CMRL has to seriously do some rethinking and set right lapses at least in the forthcoming stations. We really do not need yet another poorly designed public facility.

[This article was first published in Madras Musings, issue dated November 16 -30 and has been republished with permission. For the original article and photos, click here.]

Comments:

  1. Dinesh says:

    Instead of complaining why doesn’t a common person benefit from a mode of transportation. The more people use it the more money is going to be spent on maintenance. Take a look at the MRTS and the metro. They have done a lot more and they are in expansion mode. All everyone does is complain here.

    • Sridhar says:

      Comparison of Metro with MRTS is like comparing apples and oranges. For example, Rs 5 gets me to Beach from Thirumylai. I have to fork double that amount to get into a Metro train.

  2. T. D.Babu says:

    I really wonder why should it be taken as a complaint? It is a feedback given by the team spending so much time in public interest. We need to appreciate them for bringing to the notice of the public and the government to correct these faults and ensure safety. Will you or me accept flaws in the construction of a house we buy considering that we would be benefiting from this as a kind of shelter and proposed amenities around the flawed shelter? Let’s be thoughtful and have longer vision.

  3. Uday says:

    no body talks about chennai anymore. like kolkata, chennai has been pushed into the background with cities like delhi mumbai and bangalore only appearing in national and international “go to” cities.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Bengaluru Buzz: Rain breaks 150-day hot spell | Addressing water woes… and more

Other news of the week: Drive to increase lifespan of trees, Koramangala Valley waterway to be completed by Aug 15th and LED project revived.

Showers break 150-day hot spell Sources from the India Meteorological Department (IMD) had said that dry weather may prevail in the city till May 5th, but light showers on May 2nd brought relief. It had been a zero rainfall month in April, a first since 1983 - and one of the longest dry spells of nearly 150 days since November 2023. The rains also brought in the usual issues of water logging, power outages and traffic bottlenecks. May Day was the hottest of the month so far in 40 years, touching 38.1 degrees Celsius. Kempegowda International Airport showed the highest…

Similar Story

Mumbai Buzz: Two die in a manhole accident | Metro 3 trials begin and more…

Other news in Mumbai: Two children suffocate to death in abandoned car; Bombay HC rap for demolishing galas; Leopard captured at Vasai.

Two die, third critical after falling into manhole Mumbai continues to see tragic accidents related to manual scavenging and deadly manholes. Two people died and a third is critical after falling into a 30-foot-deep manhole in Malad. The manhole was connected to a drain pipe on the site of a private under-construction building at Pimpripada in Malad east. Raju, who was a worker at the site, fell in and after that two nearby residents, Aqib and Javed jumped to save him. When none of them came out, the locals called the fire brigade to rescue them. According to the preliminary…